Originally Posted by vj123 View Post
Below is the timeline from my MY22 G80 order. It would give a idea to anyone who wants to understand the process.

1/11 - Order in dealer bank (47)
1/24 - Order accepted, scheduled for CW11 (111)
2/07 - Order accepted, scheduled for CW10 (111)
2/09 - Scheduled for Production, CW9 (112)
2/16 - Production begins (150)
2/24 - Exterior body assembly begins (151)
2/25 - In paint booth (152)
2/28 - Entering Assembly Line (153)
2/28 - Assembly in process (154)
3/01 - Quality check
3/02 - Production completed (155)
3/02 - Ready for transport (160)
3/02 - Awaiting carrier assignment (182)
3/07 - Dispatched from factory (190)
3/11 - At port, Bremerhaven
4/08 - In transit
4/29 - At port, Charleston (193)
5/02 - In transit (195)
5/05 - At VPC, Greenville
5/05 - VPC work order closed
5/06 - PC confirms delivery date
5/31 - Performance Center Delivery

This thread (LINK) has a comprehensive summary of Performance Center Delivery.
It's crazy that it takes about 3 months after the car has already been built!